|
Air Quality Permitting
Air Pollution Control Permit to Construct
Purpose
The Permit to Construct process provides
for the review of proposed sources or proposed modifications to
existing sources of air contaminants. A Permit to Construct is issued
only if it is expected
that the proposed source or modification will comply with the
applicable rules.
Permit to Construct Required
A Permit to Construct is required for any new stationary source, or
modification to an existing source, within a source category
designated in
Section 33-15-14-01. Sources that are exempt from
obtaining a Permit to Construct are listed in
Section
33-15-14-02.13.
Construction May Not Begin Before a Permit Is Issued
No construction, installation or establishment of a
new stationary source may commence unless the owner or operator
has filed an application for and received a Permit to Construct in
accordance with
Chapter 33-15-14.
Construction, installation or establishment means:
-
For sources subject to a standard or
requirement under chapters 33-15-13, 33-15-15 (excluding increment
consumption by non-major sources), and 33-15-22, it shall have the
meaning given for construction in each of the respective chapters.
-
For all
other sources it means the placement or erection - including
fabrication, demolition or modification - of an air contaminant
emissions unit and any equipment, process, or structure that will
be used to reduce, physically or chemically change, or transmit to
the atmosphere any air contaminant. This does not include the
building that houses the source, site work, foundations or other
equipment that does not affect the amount, ambient concentration
or type of air contaminants that are emitted. With respect to a
physical change or a change in the method of operation, it means
those onsite activities which will affect an existing emissions
unit or establishment of a new unit that emits to the atmosphere.
Application Process
-
The
application forms are received by the Department and reviewed for
completeness.
-
If the
application is incomplete, the applicant will be notified of the
deficiencies. If the application is complete, the technical review
will begin.
-
After
review, the Department will issue or deny the permit.
-
The
Permit to Construct may include conditions for compliance testing,
monitoring, recordkeeping and reporting. If the conditions of the
permit to construct are satisfied, a Permit to Operate will be
issued for the source. See Permit to Operate section.
Public Notification and Participation
A 30-day public comment period is required for:
-
Affected facilities under
Chapter 33-15-13,
Emission Standards for Hazardous Air Pollutants.
-
New sources that will be
required to obtain a Permit to Operate under the Title V Permit
Program.
-
Modifications to an
existing facility that will increase the potential to emit from
the facility by the following amounts:
-
One
hundred tons [90.72 metric tons] per year or more of
particulate matter, sulfur dioxide, nitrogen oxides, hydrogen
sulfide, carbon monoxide or volatile organic compounds; or
-
Ten tons [9.07 metric
tons] per year or more of any contaminant listed under section
112(b) of the Federal Clean Air Act; or
-
Twenty-five tons [22.68
metric tons] per year or more of any combination of
contaminants listed under section 112(b) of the Federal Clean
Air Act; or
-
Sources
that the Department has determined to have a major impact on air
quality, a request for a public comment period has been received,
a significant degree of public interest exists or those sources
that request a federally enforceable permit which limits their
potential to emit.
Dispersion Modeling
Dispersion modeling for criteria
pollutants may be required
prior to issuance of a Permit to Construct in accordance with the
Criteria Pollutant
Modeling Requirements for a Permit to Construct. For
facilities with compressor engines and glycol dehydration units,
dispersion modeling may be required in accordance with the
Dispersion Modeling Requirements for Compressor Engines and Glycol
Dehydration Units.
Consultant List
A
consultant
list is maintained by the Department. Consultants wishing to
be placed on the list should contact the North Dakota Department of
Health at 701-328-5188 or email Chuck
Hyatt.
Time It Will Take To Obtain a Permit To Construct
Because the permitting process can be very detailed and can include public
participation, it can take from three months to one year to obtain
a Permit to Construct. Therefore, plan to submit your application well
before the proposed installation and start-up date of the source.
Permit-To-Construct Fees
Fees are assessed in accordance with
Section 33-15-23-02.
A filing fee of $150 must be submitted with the permit application. An
additional processing fee, based on processing costs that would
exceed $150, will be billed to the applicant.
Who Is Responsible for Obtaining a Permit
The owner or operator of the source that will be installed or
modified is ultimately responsible for obtaining the permit to
construct.
Forms
Standard permit application forms are available from
the Division of Air Quality.
Click Here for Air Pollution Control Permit to Construct
Application Forms.
Questions may be addressed to the
North Dakota Department of Health at 701.328.5188, or email
Craig Thorstenson.
Air Pollution Control Permit To Operate
Permit To Operate Required
A Permit to Operate is required for the routine
operation of an installation or source designated in Section
33-15-14-01. Those sources that received a Permit to Construct under
Section 33-15-14-02 need
to submit notification to the Department within 15 days after the date of
initial startup to satisfy the requirement to apply for a Permit to
Operate. The Permit to Operate is then issued after the conditions of the
Permit to Construct have been satisfied. For those sources that were not
issued a Permit to Construct (i.e., portable sources), an application for
a Permit to Operate must be made on forms (same as the Permit to
Construct application forms) supplied by the Department prior to
initiating operations.
Click Here for Application Forms
Types of Permits To Operate
-
Minor Source Permit
To Operate - Sources that have the potential to emit less than 100 ton/yr of a criteria
pollutant or less than 10 ton/yr of any hazardous air pollutant or
less than 25 ton/yr of any combination of hazardous air pollutants.
-
Synthetic Minor Source Permit
To Operate - Sources that have the potential to emit 100 ton/yr or greater of a
criteria pollutant, 10 ton/yr or greater of any hazardous air
pollutant, or 25 ton/yr or greater of any combination of hazardous air
pollutants, and the permittee accepts a federally enforceable limit in
the Permit to Operate that limits the potential to emit to the same
criteria specified for a minor source.
-
General Permit to Operate - A general
Permit to Operate may be issued to cover numerous similar sources
(i.e. grain elevators).
-
Title V Permit to Operate
- Sources that
emit 100 ton/yr or greater of a criteria pollutant or 10 ton/yr of a
hazardous air pollutant or 25 tons/yr or greater of any combination of
hazardous air pollutants. In addition, any source in a source category
designated by the administrator of the United States EPA also is
required to obtain a Title V permit. Sources that require a Title IV
Acid Rain Permit are issued the Title IV permit with the Title V
Permit to Operate.
Important
Note:
Sources that have received a Permit to Construct and
require a Title V Permit to Operate or Title V permit revision must file a
complete Title V application within 12 months after commencing operation.
Click Here for Title IV and Title V Forms and Supporting
Information
Public Participation/Administrative Review
Public participation (30-day comment period) is required
prior to issuing synthetic minor permits under the Minor Source Permit to
Operate Program and Title V Permit to Operate Program. Title V Permits to
Operate also require a 45-day review period by EPA.
Fees
Annual fees for a Permit to Operate are detailed in
Chapter 33-15-23.
Questions may be addressed to the North Dakota Department of Health at
701.328.5188, or email Lew Dendy. Permit to Operate Renewal Procedure
Minor Source –
Existing permits contain a condition that requires that an application for renewal be submitted to the Department no later than ninety days prior to the expiration date. As a courtesy, the Department typically sends a renewal reminder notice approximately 4 months prior to the permit expiration date. Non-receipt of this notice does not absolve a permittee of any renewal requirements. The notice will include a copy of the renewal application form (SFN-60242) and a copy of the existing permit. The renewal application form is also available on the Department website at http://www.ndhealth.gov/AQ/AirForms.htm.
To complete a renewal application, a permittee must review the existing permit and accomplish the following:
1. Verify all administrative entries in Items 1 through 4 of the existing permit and all source unit information in Item 6. Line out incorrect entries on the copy of the permit provided (or a similar copy), and enter the correct information to include changes in address, location, items of equipment, processes, etc. Use additional sheets as necessary.
2. Review the conditions of the permit listed in Item 7. Any questions about the conditions should be noted directly on the permit or on additional sheets.
3. Complete and sign the "Permit Renewal Application" form.
4. Return the signed Permit Renewal Application form and the copy of the existing permit with any changes annotated to the Department at the following address:
North Dakota Department of Health
Division of Air Quality
918 E. Divide Avenue, 2nd Floor
Bismarck, ND 58501-1947
Any questions about this process should be directed to the current air quality permit manager for your facility (as is identified on the renewal notice from the Department), or contact the Department at (701)328-5188.
Title V (Major) Source –
A permit renewal for a Title V (Major) source must be submitted at least six months, but no more than eighteen months prior to the expiration date for the permit. As a courtesy, the Department typically sends a renewal reminder notice approximately 1 year prior to the permit expiration date. Non-receipt of this notice does not absolve a permittee of any renewal requirements. The notice will include a copy of the renewal application form (SFN-60242) and a copy of the existing permit. The renewal application form is also available on the Department website at http://www.ndhealth.gov/AQ/AirForms.htm.
Return the signed Permit Renewal Application form and the enclosed permit with any changes or corrections to the Department at the following address:
North Dakota Department of Health
Division of Air Quality
918 E. Divide Avenue, 2nd Floor
Bismarck, ND 58501-1947
Also, send a copy of the permit renewal application to EPA Region 8 at:
Director, Air & Radiation Program (8P-AR)
U.S. EPA - Region 8
1595 Wynkoop Street
Denver, CO 80202-1129
Permit renewals are subject to the same procedural requirements, including those for public participation, affected state and the United States Environmental Protection Agency review, that apply to initial permit issuance.
Any questions about this process should be directed to the current air quality permit manager for your facility (as is identified on the renewal notice from the Department), or contact the Department at (701)328-5188.
|